Pneumatic tube systems are an important part of material transport in many modern facilities, especially hospitals, laboratories, pharmacies, manufacturing environments, and other buildings where documents, specimens, medications, or small materials need to move quickly between locations.
For architects, specifying a pneumatic tube system is not simply a matter of selecting equipment and showing a tube route on the plans. The system needs to be considered as part of the overall building design, including space planning, vertical transportation, structural coordination, electrical requirements, access for maintenance, and the operational needs of the facility.
When pneumatic tube infrastructure is considered early in the design process, it can be integrated more efficiently with the building. When it is added late, changes to walls, ceilings, shafts, equipment rooms, and other building systems may be required.
This guide covers the key considerations architects should understand before specifying a pneumatic tube system.
What Is a Pneumatic Tube System?
A pneumatic tube system is an automated transport network that moves carriers through a network of tubes using controlled air pressure and vacuum.
Depending on the application, carriers can transport items such as:
- Laboratory specimens
- Medications
- Documents
- Small medical supplies
- Cash or valuables
- Production samples
- Small parts and materials
- Other lightweight items
A typical system includes stations, tube runs, diverters, blowers or vacuum equipment, carriers, control systems, and supporting infrastructure.
The exact configuration depends on the building type, number of destinations, expected traffic, required delivery times, and the materials being transported.
Why Pneumatic Tube Systems Matter to Architects
Pneumatic tube systems directly affect the way certain spaces are planned and connected.
In a hospital, for example, a pneumatic tube network may connect nursing units, laboratories, pharmacies, emergency departments, operating areas, and other departments. The system therefore becomes part of the building’s internal transportation infrastructure.
Architects should consider the system alongside other major building systems rather than treating it as an isolated piece of equipment.
Early coordination can help address:
- Tube routing
- Equipment-room requirements
- Station locations
- Vertical shafts
- Ceiling spaces
- Structural penetrations
- Electrical requirements
- Maintenance access
- Fire and life-safety requirements
- Coordination with mechanical, electrical, plumbing, and other trades
1. Determine the Facility’s Transportation Requirements
The first step is understanding what the facility actually needs to transport.
Different applications can have very different requirements. A laboratory-focused system may prioritize specimen transportation, while a hospital-wide network may need to support multiple departments and high traffic volumes.
Architects should work with the owner and system designer to understand:
- What materials will be transported?
- Where will items originate?
- Where do they need to go?
- How frequently will carriers be sent?
- What peak traffic periods are expected?
- How quickly do items need to arrive?
- How many stations are required?
- Will the system need to accommodate future expansion?
Understanding these requirements early helps determine the appropriate system architecture and building infrastructure.
2. Plan Tube Routes Early
One of the most important architectural considerations is routing.
Pneumatic tube systems require dedicated pathways throughout the building. Depending on the project, tubes may run above ceilings, through walls, within vertical shafts, or through other designated service spaces.
Routing should be coordinated with other building systems before finalizing the architectural layout.
Potential conflicts can occur with:
- HVAC ductwork
- Plumbing
- Electrical conduit
- Fire sprinkler systems
- Structural members
- Lighting
- Ceiling systems
- Access panels
- Other low-voltage systems
A route that appears straightforward during conceptual design may become difficult after other trades are coordinated.
For this reason, pneumatic tube routing should be reviewed during the design development and coordination phases rather than waiting until construction.
3. Consider Vertical Transportation
Multi-story buildings require additional planning because the pneumatic tube network may need to move between floors.
Vertical tube runs often require dedicated shafts or carefully coordinated pathways.
Architects should identify potential vertical routes early and consider:
- Shaft dimensions
- Tube quantity
- Future capacity
- Access requirements
- Fire-rated construction
- Penetrations between floors
- Coordination with elevators and other vertical systems
A well-planned vertical pathway can simplify installation and future maintenance.
4. Station Locations Should Follow Workflow
The location of each pneumatic tube station should be based on how people actually use the facility.
Simply placing stations where there is available wall space may create operational problems.
For example, in a healthcare environment, a station should be convenient for staff who regularly send or receive carriers. It should not interfere with patient circulation, equipment movement, emergency access, or other critical activities.
When planning station locations, architects should consider:
- Staff workflow
- Visibility
- Accessibility
- Clear floor area
- Nearby equipment
- Door swings
- Corridor circulation
- Infection-control requirements where applicable
- Maintenance access
The station should become part of the room’s functional layout rather than an afterthought.
5. Coordinate Station Dimensions With Interior Design
Pneumatic tube stations are physical architectural elements and need to be coordinated with interior finishes.
Depending on the system and station type, architects may need to account for:
- Wall construction
- Cabinetry
- Countertops
- Millwork
- Finishes
- Electrical connections
- Data or control connections
- Required clearances
Station elevations and dimensions should be reviewed before interior details are finalized.
This is particularly important in highly designed environments where millwork and equipment are tightly integrated.
6. Understand Equipment and Blower Requirements
The pneumatic tube system requires mechanical equipment to create the airflow needed to move carriers.
Equipment may include blowers, vacuum units, diverters, controls, and other system components.
Architects should coordinate the location of this equipment with the appropriate engineering disciplines.
Important considerations can include:
- Equipment-room location
- Available floor area
- Electrical service
- Ventilation
- Heat generation
- Noise
- Maintenance access
- Equipment replacement access
The equipment room should not only fit the initial installation. There should also be sufficient access for technicians to inspect, service, and replace components when necessary.
7. Consider Noise and Acoustic Requirements
Pneumatic tube systems use air movement and mechanical equipment, which means acoustic considerations can be important.
The impact will depend on the type of system, equipment location, building construction, and proximity to occupied spaces.
In facilities such as hospitals, patient rooms and other quiet areas may require additional consideration.
Architects should coordinate equipment locations and acoustic requirements with the engineering and system-design teams to determine whether isolation or other measures are appropriate.
8. Coordinate Electrical and Controls Requirements
Pneumatic tube systems require electrical power and control infrastructure.
The specific requirements depend on the selected equipment and system configuration, so architects should coordinate with the project engineers and system provider rather than assuming generic electrical requirements.
Planning may include:
- Dedicated power
- Control wiring
- Communication infrastructure
- Equipment connections
- Station connections
- Emergency power where required by the project
- Integration with facility systems where applicable
These requirements should be incorporated into the project’s electrical and technology coordination documents.
9. Plan for Maintenance Access
A pneumatic tube system is designed to operate continuously over the life of a facility. Maintenance therefore needs to be considered during the design stage.
Technicians may need access to:
- Blower equipment
- Diverters
- Tube sections
- Station components
- Control equipment
- Other serviceable components
Architects should avoid creating routes where critical components are permanently concealed behind inaccessible finishes.
Access panels, equipment clearances, service spaces, and removable ceiling sections may need to be coordinated as part of the architectural design.
10. Account for Structural Coordination
Tube systems can require penetrations through walls, floors, ceilings, and other building elements.
Structural coordination should occur before field installation.
The project team should identify:
- Required floor penetrations
- Wall penetrations
- Shaft openings
- Structural conflicts
- Support requirements
- Fire-rated assemblies affected by penetrations
The system supplier and structural engineer should coordinate penetration and support requirements according to the final system design.
11. Review Fire and Life-Safety Requirements
Pneumatic tube systems can pass through multiple fire compartments and floors. This makes fire and life-safety coordination an important part of the design.
Architects should review how tube penetrations interact with:
- Fire-rated walls
- Fire-rated floors
- Smoke compartments
- Fire barriers
- Firestopping
- Other code-required assemblies
Specific requirements vary by project, building type, jurisdiction, and applicable codes.
The final design should be reviewed with the project’s code consultant, fire-protection professionals, engineers, and system provider.
12. Think About Future Expansion
One of the most overlooked considerations is future capacity.
A facility may initially require a certain number of stations and tube routes, but operational requirements can change.
Future departments may be added, spaces may be renovated, or transportation volumes may increase.
Architects can help accommodate future expansion by considering:
- Spare capacity in shafts
- Accessible routing
- Future station locations
- Equipment capacity
- Additional tube pathways
- Expansion zones
- Access for future modifications
Building flexibility into the initial design can reduce disruption during future renovations.
13. Coordinate With the Entire Project Team
Pneumatic tube systems touch multiple areas of a building project.
Successful coordination may involve:
- Architect
- Owner
- MEP engineers
- Structural engineer
- General contractor
- Electrical contractor
- Low-voltage contractor
- Interior designer
- Fire-protection professionals
- Pneumatic tube system provider
The earlier these groups coordinate, the easier it becomes to resolve conflicts before construction.
14. Specify Performance, Not Just Equipment
Architectural specifications should clearly communicate the intended system performance and project requirements.
Depending on the project, the specification may address:
- System type
- Station requirements
- Carrier requirements
- Tube sizes
- Performance requirements
- Controls
- Installation
- Testing
- Commissioning
- Training
- Documentation
- Warranty
- Maintenance
The exact specification should be developed around the project’s operational requirements and the selected system.
15. Installation and Commissioning Should Be Part of the Plan
The project does not end when the tubes and stations are installed.
A pneumatic tube system typically needs testing and commissioning before the facility begins normal operation.
Architects and project teams should understand the importance of:
- Installation verification
- System testing
- Station testing
- Carrier testing
- Controls verification
- Integration testing where applicable
- Operator training
- Final documentation
A coordinated commissioning process helps verify that the installed system operates as intended.
Common Mistakes to Avoid
Several common design decisions can make pneumatic tube installation more difficult than necessary.
Adding the System Too Late
Waiting until construction documents are nearly complete can make routing and space coordination difficult.
Treating Tube Routes as Generic MEP Space
Tube routing has specific requirements. It should be coordinated based on the selected system rather than simply assuming that unused ceiling space will be sufficient.
Ignoring Maintenance
A component that cannot be accessed easily can become a long-term maintenance problem.
Choosing Station Locations Without Workflow Analysis
Stations should support the people and departments using them.
Not Planning for Future Growth
Leaving no room for future expansion can make later modifications expensive and disruptive.
Questions Architects Should Ask Before Specifying a Pneumatic Tube System
Before finalizing the design, consider asking the system provider and project team:
- What materials will the system transport?
- What are the expected traffic volumes?
- How many stations are required?
- Where should stations be located based on workflow?
- What tube routing options are available?
- What shaft space is required?
- What equipment-room space is needed?
- What electrical and control requirements apply?
- What maintenance access is required?
- How will fire-rated assemblies be addressed?
- What acoustic considerations apply?
- What future expansion should be accommodated?
- What testing and commissioning will be required?
- What information should be included in the construction documents?
- Who will coordinate final system installation?
Final Thoughts
Pneumatic tube systems can become an important part of a building’s internal transportation infrastructure, but their success depends heavily on planning and coordination.
For architects, the key is to consider the system early. Tube routes, station locations, equipment spaces, vertical pathways, structural penetrations, electrical requirements, maintenance access, and future expansion should all be reviewed before the building design is finalized.
Working with an experienced pneumatic tube system provider during the design process can help identify requirements early and reduce conflicts during construction.
The goal is not simply to fit a pneumatic tube system into a finished building. The goal is to integrate the system into the architecture so that it supports the facility’s workflow, remains accessible for maintenance, and can operate effectively over the long term.